AI Meets the Grid: Interconnection Queue Analysis in PJM and ERCOT

Over 300 GW of generation is queued in PJM and ERCOT, but data center projects face 3 to 4 year waits. Relae maps what is moving, what is stalling, and why.

By continuing, you are agreeing to the Relae Terms of Service and Privacy Policy. You will also join our mailing list for marketing updates.

Oops! Something went wrong while submitting the form.

Data centers requiring over 10 GW of power were announced in PJM and ERCOT in just six months. Getting that power online means navigating backlogged and slow interconnection queues. This analysis maps what is in the queue across both markets, which technologies are moving and which are stalled, and what the latest policy shifts mean for achieving speed to power.

What's Inside

  • More than 300 GW of generation and storage across roughly 1,500 projects are waiting in the PJM and ERCOT queues, enough capacity on paper to meet projected data center demand through 2030.
  • But, active projects in data center load growth zones across both markets are waiting 3 to 4 years in the interconnection queue.
  • Renewables and storage make up 77% of PJM's active queue and 87% of ERCOT's, while natural gas projects move through the queue significantly faster.
  • After the One Big Beautiful Bill Act, monthly gas entries to ERCOT's queue increased 150%, while renewable withdrawals followed in both markets.

‍

Authors
Derya Eryilmaz, PhD
Vice President
,
Power
Dr. Derya Eryilmaz is an energy economist and Vice President of Power at Relae. She provides expertise in the analysis of power market design, grid modeling, strategy for data center energy transition through emerging and renewables investments and flexible load.
Liam Kilroy
Energy Data Scientist
As a Data Scientist at Relae, Liam combines domain expertise in electricity markets with data science methods to build tools, perform research, and advise internal and external clients on a variety of energy and sustainability topics.